Fraser Morgan Dewatering and Infrastructure Project
Construct a multi-tiered Dewatering system as well as perform upgrades to an existing Sandfill system.
WORK COMPLETED
- Installation of three pump stations
- Installation of two Agitator Sumps
- Installation of a Vertical Settler and Decant Area (which involved the installation of a large stainless steel reducing cone in an existing raise to separate the solids from the spent mine water and send them to a decanting area for drying and storage)
- Installation of all communications and electrical components including a substation
Customer
Sudbury Integrated Nickel Operations
Services Provided
- Electrical Installations
- Mechanical Installations
- Underground Construction